All articles Simulators

What a simulator activation needs on site: space, power, access and lead time

Language: Español 日本語

Four site facts decide whether an activation is possible before anybody discusses the idea: the footprint including the space a person needs behind the seat, the power available at the position, how the equipment physically gets to that position, and how many hours you have to build. Any one of them can end a plan at the door.

Footprint is not the size of the rig

The dimension that matters is the working footprint: the rig, the space a person needs to get in and out without asking anyone to move, the position the host stands in, and the queue. A rig quoted at two metres by one usually needs closer to three by two before it can actually be operated.

The version of this that catches people is the queue. A line that has nowhere to form spills into the aisle, and an aisle is not yours: venues move you, and they move you at the busiest hour.

Power is a question about the position, not the building

Every venue has power. The question is what is available at the exact position you have been allocated, on a circuit that is not shared with something that spikes. Ask for the supply at your stand number, in amps, and ask what else is on it.

Get this wrong and the failure is intermittent, which is worse than total: the rig works all morning and drops out when the neighbouring stand switches on a lighting rig, and everyone assumes the equipment is faulty.

The door

More activations die at a doorway than at a budget meeting.

Freight lifts, loading bay height, the width of the corridor to the hall, whether there is a step, whether there is a ramp, and whether the venue permits the equipment to move during public hours. A build that fits the stand and does not fit the route to it is a build that does not happen.

Measure the narrowest point of the whole path, not the door of the hall. And ask in writing.

Lead time, and what it is actually made of

Where the weeks go
StageWhat determines it
Site confirmationFloor plan, power drawing and access route in writing from the venue, not from the organiser's sales deck
Content and brandingAny custom livery, custom track or branded interface. The longest item on most projects
Build and testThe rig assembled and run end to end somewhere other than the venue, before it ships
On-site buildHours, not days, and usually overnight. This is the number the venue gives you and it is not negotiable

A short lead time does not make a project impossible. It makes custom content impossible, which is a different conversation and a much better one to have in week one than in week six.

Questions people ask

How much space does a racing simulator need at an event?
More than the rig measures. The working footprint includes the space a person needs to get in and out, the position the host stands in, and somewhere for the queue to form. A rig quoted at two metres by one usually needs closer to three by two to be operated.
What power does a simulator activation require?
The question is not what the venue has but what is available at your exact allocated position, in amps, and what else shares that circuit. A shared circuit produces intermittent failure, which everyone mistakes for faulty equipment.
What is the most common reason an activation cannot be installed?
Access. Freight lift dimensions, loading bay height, corridor width, steps, and whether the venue permits movement during public hours. Measure the narrowest point of the entire route, not the door of the hall, and get it in writing.

Keep reading